Saturday, September 29, 2012

A Productive Week

September 24-28:  It's starting to look like something. Mark and Jerry Favreau raced against the rain this week and made some headway with the framing.  They finished the week by putting the sub-floor down in the pouring rain.  Stay tuned for the walls next week.  









Yes, that's a hose.  Mark installed a pump that is pumping out water not nearly as fast as it is filling the basement.  Bruce rigged up a big tarp and put up temporary gutters at the end of the house, which are helping immensely.  This weather needs to change.  Notice the beautiful trees that will be out Mimi's kitchen and dining room windows.

Monday, September 24, 2012

Completion of the Foundation Phase

September 24, 2012


The basement floor was poured on Friday, 9/20, marking the completion of the foundation work.  We are praying for dry weather but come over for a swim if our prayers aren't heard.


Other updates:  Over the past couple of weeks, Bruce got the basement windows and storms done, got started on customizing a very cool entry door, and started building the window well for the basement egress window.   

Tuesday, September 4, 2012

Mimi's New House



WELCOME TO MIMI'S NEW HOUSE BLOG

July 2012:  The plans for Mimi's new house are final:




First Week of August 2012: 

Construction began in early August when Bruce and I removed the shingles from the end of the house to make way for the addition.  We were happy to discover that it was possible to do so without damaging them so that they can all be re-used.  We also built the "dipping pavilion" to pre-dip the new cedar shingles (which came from a small shingle mill in East Corinth via Craig's List).  We'll fill the rack up every weekend until they are all done. 








August 15th:

The real fun began when the excavator arrived at 7:00 am.  (There were moms with kids in the yard for days watching.)  The hole was dug, the footings were poured, and the walls were poured over the course of a couple of weeks.  

digging the hole


pouring the footings

erecting the forms for the basement walls

pouring the walls

removing the tools - the concrete work is done

September 1st:

The next step was framing in all the basement windows, which Bruce did over Labor Day weekend.  (We are making our own basement windows because it was the only way to avoid vinyl.)  There will be a break in the action now while the cement cures, we figure out the drainage, and the existing sewer line is replaced (nasty surprise).  We are hoping to see lumber arrive by mid-September.  Mimi needs to get home from Africa to check it out!




notice the giant hole into our basement, thanks to some really big guys with a really big saw



TO BE CONTINUED!